Planned work on changes in the Berzarina data center MSK-1 02/20/24 from 2024-02-20 00:00 EAT to 2024-02-20 03:00 EAT
Scheduled maintenance
Bare metal
Pools
MSK-1
Services
Network
2024-02-20 00:00 EAT
· 3 hours
Updates
Scheduled
February 13, 2024 · 14:16 EAT
On 02/20/2024 from 00:00 to 03:00 (GMT/UTC +3), planned work will be carried out to modernize the infrastructure in the Berzarina data center.
It is planned to reduce the level of router redundancy for the entire duration of work to N+0 for shared subnets and for dedicated subnets with vrrp enabled.
Expect 2 interruptions of up to 10 seconds each for dedicated subnets without vrrp enabled and geo-distributed subnet services.
There are no plans to shut down equipment.