Planned work on changes in the Berzarina data center MSK-1 02/20/24 from 2024-02-20 00:00 MSK to 2024-02-20 03:00 MSK

Scheduled maintenance Bare metal Pools Services Network
2024-02-20 00:00 MSK · 3 hours

Updates

Resolved

This maintenance has been concluded as planned.

February 20, 2024 · 03:00 MSK
Started

This maintenance is now starting as planned.

February 20, 2024 · 00:00 MSK
Scheduled

On 02/20/2024 from 00:00 to 03:00 (GMT/UTC +3), planned work will be carried out to modernize the infrastructure in the Berzarina data center.

It is planned to reduce the level of router redundancy for the entire duration of work to N+0 for shared subnets and for dedicated subnets with vrrp enabled.

Expect 2 interruptions of up to 10 seconds each for dedicated subnets without vrrp enabled and geo-distributed subnet services.

There are no plans to shut down equipment.