Scheduled work on electrical equipment of the data center Berzarina-1 from 2024-04-08 09:00 MSK to 2024-04-11 18:00 MSK

Notification Bare metal Pools Services Dedicated Servers
2024-04-08 09:00 MSK · 3 days, 9 hours, 1 second

Updates

Resolved

This maintenance has been concluded as planned.

April 11, 2024 · 18:00 MSK
Started

This maintenance is now starting as planned.

April 8, 2024 · 09:00 MSK
Scheduled

Planned work to modernize electrical equipment will be carried out at the Berzarina-1 data center.

From 04/08/2024 to 04/11/2024 in the period from 06:00 to 15:00 UTC, during scheduled work, one power supply input will be disconnected in some server racks, which will result in a decrease in the level of redundancy.

These works will not affect the operation of servers with one power supply; if the server has two power supplies, then one of them will be turned off, while the equipment will continue to operate.

If your equipment falls under the specified works, you will receive a corresponding notification in the control panel my.servercore.com

April 4, 2024 · 12:00 MSK