Planned work to modernize the power supply in location SPB-4, SPB-5 from 2024-04-17 10:00 MSK to 2024-04-17 17:30 MSK

Notification Bare metal Pools Data centers Infrastructure Electricity
2024-04-17 10:00 MSK · 7 hours, 30 minutes

Updates

Resolved

This maintenance has been concluded as planned.

April 17, 2024 · 17:30 MSK
Started

This maintenance is now starting as planned.

April 17, 2024 · 10:00 MSK
Scheduled

On 04/17/2024, from 10:00 to 17:30 (UTC+3), scheduled work will be carried out at the SPB-4, SPB-5 location aimed at modernizing the power supply.

The level of redundancy will be reduced. No impact on equipment operation is expected.

April 11, 2024 · 12:02 MSK

← Back