Planned works on electrical equipment in data center Dubrovka-2 29.07.24 from 2024-07-29 06:30 to 2024-07-29 15:00

Scheduled maintenance Bare metal Pools SPB-5
2024-07-29 06:30 · 8 hours, 30 minutes

Updates

Times are shown in Africa/Abidjan timezone
Resolved

This maintenance has been concluded as planned.

July 29, 2024 · 15:00
Started

This maintenance is now starting as planned.

July 29, 2024 · 06:30
Scheduled

In the data center “Dubrovka-2” will be carried out scheduled work to upgrade electrical equipment. 29.07.24g. in the period from 06:30 to 10:00 (UTC+0) will be disconnected one power supply input, in the period from 11:00 to 15:00 (UTC+0) will be disconnected input 2, which will entail a reduction in the level of redundancy.

The work of servers with one power supply unit will not be affected by these works, if the server has two power supplies, one of them will be disconnected, at the same time, the equipment will continue to work.