Planned works on electrical equipment in data center Dubrovka-2 29.07.24 from 2024-07-29 09:30 EAT to 2024-07-29 18:00 EAT
Notification
Bare metal
Pools
2024-07-29 09:30 EAT
· 8 hours, 30 minutes
Updates
Scheduled
July 23, 2024 · 12:39 EAT
In the data center “Dubrovka-2” will be carried out scheduled work to upgrade electrical equipment. 29.07.24g. in the period from 06:30 to 10:00 (UTC+0) will be disconnected one power supply input, in the period from 11:00 to 15:00 (UTC+0) will be disconnected input 2, which will entail a reduction in the level of redundancy.
The work of servers with one power supply unit will not be affected by these works, if the server has two power supplies, one of them will be disconnected, at the same time, the equipment will continue to work.