Planned work on modernization of electrical equipment in SPB-1 from 2024-09-26 08:00 MSK to 2024-09-26 18:00 MSK
Notification
Bare metal
Pools
Data centers
Infrastructure
Electricity
2024-09-26 08:00 MSK
· 10 hours, 1 second
Updates
Scheduled
September 24, 2024 · 15:35 MSK
From 08:00 26.09.24 to 18:00, scheduled electrical equipment upgrades will be carried out at location SPB-1.
During the work, one power supply input will be disconnected, which will reduce the level of redundancy.
The changes will not affect the operation of the server equipment.
← Back