Emergency work to reconfigure the BGP interface from 2025-01-24 12:00 EAT to 2025-01-24 16:00 EAT

Scheduled maintenance Bare metal Pools TAS-1 TAS-2 Services Network Cloud Platform Pools uz-1a uz-2a Services Network Data centers Tashkent, Uzbekistan Infrastructure Network External network External network
2025-01-24 12:00 EAT · 4 hours

Updates

Resolved

This maintenance has been concluded as planned.

January 24, 2025 · 16:00 EAT
Update

The work was cancelled.
The new date and time will be indicated in the next notification update in the status panel.

January 24, 2025 · 14:24 EAT
Scheduled

Hello.

On January 24, 2025, urgent work will be carried out to reconfigure the joint with the Uzbek piercing.

As part of these works, the BGP session will be reconfigured through an intermediate TAS-IX operator.

Work period: from 01/24/2025 14:00 to 01/24/2025 18:00 UTC+5.
Expected consequences:

  • temporary deterioration of connectivity between network participants in Uzbekistan and lack of access to Sharq Telecom operator;
  • access to the global Internet will continue to function normally.

We apologize for any inconvenience.

January 24, 2025 · 10:49 EAT