Planned shutdown of the first power supply input in Dubrovka-1 from 2025-03-24 09:00 EAT to 2025-04-18 10:00 EAT

Scheduled maintenance Bare metal Pools Services Dedicated Servers
2025-03-24 09:00 EAT · 3 weeks, 4 days, 1 hour

Updates

Started

This maintenance is now starting as planned.

March 24, 2025 · 09:00 EAT
Scheduled

In order to improve the quality of our services, scheduled electrical equipment upgrade works will be carried out in the Dubrovka-1 data center from 24.03.2025 to 18.04.2025.

During the work, one power supply input will be disconnected.

Expected impact:

  • reduction in the level of power supply redundancy in server racks.

The operation of servers with one power supply unit will not be affected by these operations.
If the server has two power supplies, one of them will be disconnected, but the equipment will continue to operate.

March 20, 2025 · 12:45 EAT