Reduction of power supply redundancy in DC Tsvetnaya-2 (Availability Zone No.1) from 2025-04-02 15:19 EAT

Scheduled maintenance Data centers Infrastructure Redundancy
2025-04-02 15:19 EAT · 2 days, 7 hours, 7 minutes

Updates

Scheduled

Since 15:19 UTC+3 in DC Tsvetnaya-2 (Availability Zone #1) and up to the present time, the power backup level from the city has been reduced to N.
No unavailability or degradation of services is expected.

The engineering team is already making all arrangements to resume power from the additional input, but the work may take up to several days to complete.
We will notify you additionally about the return of the level to standard N+1.

April 2, 2025 · 20:09 EAT

← Back