Scheduled maintenance at the Tsvetochnaya-2 from 2026-11-16 10:00 EAT to 2026-11-16 20:00 EAT
Scheduled maintenance
Bare metal
Pools
SPB-2
Data centers
Infrastructure
Electricity
2026-11-16 10:00 EAT
· 10 hours
Updates
Scheduled
November 3, 2026 · 17:01 EAT
Work to upgrade the power supply system, involving the disconnection of one power feed, is scheduled at the Tsvetochnaya-2 site starting at 10:00 (UTC+3) on November 16, 2026, and continuing until completion.
During the work, equipment with two power supplies will be powered by the second feed. Equipment with a single power supply will be switched to the active feed if the rack is equipped with an automatic transfer switch (ATS).
No server shutdowns are planned during the work.