Scheduled maintenance at SPB-2 from 2026-12-02 12:00 +05 to 2026-12-02 22:00 +05
Scheduled maintenance
Bare metal
Pools
SPB-2
Data centers
Infrastructure
Electricity
2026-12-02 12:00 +05
· 10 hours
Updates
Scheduled
November 27, 2026 · 19:34 +05
On 02.12.2026 at the SPB-2 facility, work is scheduled from 10:00 until completion (UTC+3) to upgrade the power supply scheme by disconnecting one power feed.
During the maintenance, the power supply redundancy level is expected to be reduced to N+0.
No equipment downtime is expected.