2024-10-24
Scheduled software update work for the Cloud Platform from 2024-10-24 05:00 MSK to 2024-10-24 08:00 MSK
2024-10-22
Scheduled software update work for the Cloud Platform from 2024-10-22 05:00 MSK to 2024-10-22 08:00 MSK
2024-10-17
Planned work on upgrading the infrastructure of the Cloud platform in the ru regions from 2024-10-17 10:00 MSK to 2024-10-17 12:00 MSK
2024-10-16
Planned work on upgrading the infrastructure of the Cloud platform in the ru-7 pool from 2024-10-16 20:00 MSK to 2024-10-16 21:00 MSK
2024-10-16
Scheduled work on updating system software for DBaaS clusters from 2024-10-16 17:00 MSK to 2024-10-16 20:00 MSK
2024-10-16
Problems with the global router network in the ru-2 pool
2024-10-15
Planned work on upgrading the infrastructure of the Cloud platform in the ru-2 pool, 10/15/2024 from 2024-10-15 19:00 MSK to 2024-10-16 03:00 MSK
2024-10-11
Problems with network availability, ru-2
2024-10-10
Planned work to improve the stability of the control panel for dedicated servers. from 2024-10-10 23:00 MSK to 2024-10-11 01:00 MSK
2024-10-10
Scheduled work in the Cloud platform, gis-1 from 2024-10-10 20:00 MSK to 2024-10-10 21:30 MSK
2024-10-04
Issues with creating VMs in the Cloud Platform
2024-10-03
Planned work to improve stability of the control panel for dedicated servers from 2024-10-03 23:00 MSK to 2024-10-04 01:00 MSK
2024-10-01
Planned work to improve the stability of the control panel for dedicated servers from 2024-10-01 23:00 MSK to 2024-10-02 00:00 MSK
2024-09-26
Planned work on modernization of electrical equipment in SPB-1 from 2024-09-26 08:00 MSK to 2024-09-26 18:00 MSK
2024-09-24
Planned work to improve the stability of the control panel for dedicated servers from 2024-09-24 23:00 MSK to 2024-09-25 00:00 MSK
2024-09-22
Failure of the router in the ru-2 pool
2024-09-19
Scheduled work on updating system software for DBaaS clusters from 2024-09-19 21:00 MSK to 2024-09-19 23:59 MSK
2024-09-19
Unavailability of virtual machines and dedicated servers in uz-2/TAS-2
2024-09-18
Problems with DNS records sync
2024-09-14
Problems with creating Kubernetes clusters in the kz-1 location
2024-09-10
Planned works on infrastructure modernization in the Berzarina-1 data center. from 2024-09-10 00:00 MSK to 2024-09-10 04:00 MSK
2024-09-09
Planned work on upgrading the Cloud platform from 2024-09-09 07:00 MSK to 2024-09-09 08:00 MSK
2024-09-05
Scheduled work in the Cloud platform, gis-1 from 2024-09-05 15:00 MSK to 2024-09-05 16:30 MSK
2024-09-02
Planned infrastructure modernization works in the SPB-3 location from 2024-09-02 23:00 MSK to 2024-09-03 04:00 MSK
2024-09-02
Problems displaying current resource consumption
2024-09-02
Problems in operation of the DNS
2024-09-01
Problems in operation of the control panel
2024-08-31
Problems in operation of the control panel
2024-08-31
Problems with network availability, uz-2
2024-08-30
Scheduled infrastructure modernization works in the Dubrovka-1 data center from 2024-08-30 00:00 MSK to 2024-08-30 03:00 MSK
2024-08-28
Unavailability of LAN interfaces in the Dubrovka 3 data center (SPB-3)
2024-08-23
Unavailability of network drives of the Cloud platform, uz-1
2024-08-20
Scheduled work on electrical equipment in the Tsvetochnaya-2 data center (SPB-2) from 2024-08-20 23:00 MSK to 2024-08-21 09:00 MSK
2024-08-20
Unavailability of UZ-1/UZ-2 control
2024-08-19
Planned works on electrical equipment in data center Dubrovka-2, 08/01/2024 from 2024-08-19 09:30 MSK to 2024-08-19 18:00 MSK
2024-08-13
Scheduled work on electrical equipment in the Tsvetochnaya-2 data center (SPB-2) from 2024-08-13 23:00 MSK to 2024-08-14 09:00 MSK
2024-08-13
Scheduled work on electrical equipment in the Dubrovka-2 data center from 2024-08-13 09:30 MSK to 2024-08-13 18:00 MSK
2024-08-08
Planned work on infrastructure modernization in the ru-9 Cloud Platform pool from 2024-08-08 21:00 MSK to 2024-08-08 23:59 MSK
2024-08-08
Scheduled work on electrical equipment in the Dubrovka-2 data center from 2024-08-08 09:30 MSK to 2024-08-08 18:00 MSK
2024-08-06
Planned work to modernize the infrastructure in the Berzarina-1 data center from 2024-08-06 21:00 MSK to 2024-08-07 01:00 MSK
2024-08-05
Planned work on the modernization of server equipment in SPB-2 from 2024-08-05 23:00 MSK to 2024-08-06 04:00 MSK
2024-08-02
Planned works on electrical equipment in data center Dubrovka-2, 08/02/2024 from 2024-08-02 06:30 MSK to 2024-08-02 15:00 MSK
2024-07-31
Planned works on electrical equipment in data center Dubrovka-2 31.07.24 from 2024-07-31 09:30 MSK to 2024-07-31 18:00 MSK
2024-07-30
Scheduled work SPB-3 from 2024-07-30 09:30 MSK to 2024-07-30 18:00 MSK
2024-07-30
Planned works on electrical equipment in data center Dubrovka-2 30.07.24 from 2024-07-30 09:30 MSK to 2024-07-30 18:00 MSK
2024-07-29
Planned work to improve the stability of the control panel for dedicated servers from 2024-07-29 20:00 MSK to 2024-07-29 23:00 MSK
2024-07-29
Planned works on electrical equipment in data center Dubrovka-2 29.07.24 from 2024-07-29 09:30 MSK to 2024-07-29 18:00 MSK
2024-07-27
Control panel malfunction
2024-07-25
Planned work on upgrading the infrastructure for CRaaS from 2024-07-25 09:20 MSK to 2024-07-26 00:00 MSK
2024-07-22
Transferring planned migration work ru-9a from 2024-07-22 19:00 MSK to 2024-07-23 01:00 MSK